Granitowa St. to be open for traffic shortly
Marta Kufel

As of 28 November, the currently closed section of Granitowa St. will again be open for traffic.
Works on the adjustment of conflicting underground facilities have been completed. Carriageway construction works are still being performed along Granitowa St. Starting from Saturday, 28 November, passage through the currently closed section of the street will be reinstated. At the same time, due to the changed traffic arrangement, traffic on the Zdroje-Podjuchy route will be directed through the traffic circle, along the new carriageway line in the direction of the A6 motorway, and further along Marmurowa St.
Public transport
Due to implementing the next stage of the redevelopment of the junction of Floriana Krygiera St. and Granitowa St., and introducing temporary traffic arrangement in the building site, the following changes to public transport operations are to be introduced starting from 28 November 2020:
1. Lines 64, 66, and 533 (towards Dąbie and Osiedle Bukowe), along a section Klucz Autostrada - Podjuchy - Granitowa, will be accelerated by 1 minute in relation to the timetable. The current synchronised departure times of lines 64, 66 and 66 will be retained.
2. Lines 64, 66 and 533 (towards Podjuchy and Klucz) along a section Granitowa - Podjuchy - Klucz Autostrada will be delayed by 1 minute in relation to the current timetable.
3. Line 61 (towards Dworzec Główny (Owocowa)), along a section Podjuchy - Granitowa, will be accelerated by 1 minute in relation to the current timetable
4. Line 61 (towards Podjuchy), from the Granitowa bus stop, will be delayed by 1 minute in relation to the current timetable.
News from the construction site
During the upcoming days, carriageway construction works and paving works will be carried out in the Granitowa St. and the traffic circle area. As part of bridge works, the development of supports will be continued. Electrical-power and communication-conduit works will also be carried out.
About the project
The project includes the development of a junction with a traffic circle, with traffic lights and the redevelopment of Krygiera and Granitowa St. located in the vicinity of the junction. As part of the works, the existing road bridge over the Regalica River, currently out of service, will be demolished. A new river crossing will be provided instead. The works will also include the construction of pavements and cycling paths, road signs and traffic safety facilities, a storm drainage system, lighting and noise barriers. The cost of the project is PLN 104m. The contractor is the consortium of Roverpol sp. z o.o. and Rover Infrastructure S.A. The works are due to be completed in the first half of 2021.
The project is financed from the European Regional Development Fund as part of the Infrastructure and Environment Operational Programme 2014-2020. The co-financing amount is PLN 72 797 093.95.